The OK-ELEC exam has 100 questions and runs 4 hours.

These 10 free OK-ELEC questions are organized by exam domain, so you can see how each part of the Oklahoma Unlimited Electrical Journeyman Examination blueprint is tested. Reveal the answer and explanation under each question.

Domain 1: General Knowledge

Question 1

An industrial facility holds an Oklahoma annual electrical permit for alterations to an already-approved installation. During the permit term, electricians complete 14 separately identifiable alterations. At the end of the term, the annual-permit procedure requires the permit holder to:

Show answer & explanation

Correct answer: B - File the detailed alteration record and account for the fee for each individual permit

Domain 2: General Electrical Knowledge

Question 2

At a 120/240-V single-phase panel, L1-to-L2 remains 240 V. With several 120-V loads operating, L1-to-neutral measures 78 V and L2-to-neutral measures 162 V; the two readings shift when loads are switched. The most likely fault is:

Show answer & explanation

Correct answer: D - An open or high-resistance connection in the neutral

Question 3

A leakage-capable clamp meter reads 18.0 A when clamped around the ungrounded conductor of a single-phase load. When clamped around all circuit conductors together, including the neutral, it reads 1.1 A. The 1.1-A residual indicates that:

Show answer & explanation

Correct answer: A - Some current is returning on a path outside the clamped circuit conductors

Domain 3: Electrical Installation Requirements

Question 4

A technician services a 480Y/277-V panelboard. With the cover removed, exposed live parts are on one side of the working space and a concrete wall is directly opposite. The clear depth is 40 inches. The working-space installation is:

Show answer & explanation

Correct answer: C - The space is deficient because Condition 2 at 277 V to ground requires 42 inches

Domain 4: Services, Feeders, and Branch Circuits

Question 5

At a one-family dwelling in Oklahoma, a listed 240-V, single-phase, 30-A outdoor air-conditioning condensing unit is replaced in kind. The circuit is 120 V to ground, and no local rule is more stringent. Under Oklahoma's adoption of NEC 210.8(F), the correct conclusion is:

Show answer & explanation

Correct answer: A - The outlet supplying the listed HVAC equipment remains excepted; 210.8(F) alone does not require GFCI protection

Question 6

A listed rooftop air-conditioning unit is marked Minimum Circuit Ampacity 31 A and Maximum Overcurrent Protection 50 A. No other marking restricts the protective-device type. Select the branch-circuit arrangement that respects both nameplate values.

Show answer & explanation

Correct answer: D - Conductors with at least 31-A allowable ampacity and a 50-A breaker

Domain 5: Overcurrent Protection

Question 7

Available fault current at the line terminals of a branch circuit breaker is 22 kA. The panel main is rated 25 kA interrupting, but the branch breaker is rated 10 kA interrupting, and the equipment has no listed series rating. How should the branch-breaker arrangement be evaluated?

Show answer & explanation

Correct answer: B - It is not acceptable; the branch device needs a sufficient individual rating or a listed series combination

Question 8

A 300-A feeder supplies a 25-foot tap serving an 82-A calculated load. The tap is protected from physical damage and terminates in a single 90-A circuit breaker. Calculate the minimum allowable ampacity of the tap conductors under the 25-foot tap rule.

Show answer & explanation

Correct answer: C - 100 A

Domain 6: Grounding and Bonding

Question 9

A single rod electrode is fully installed, and a resistance test measures 38 ohms to earth. The contractor does not plan additional resistance testing. The minimum code-compliant next step is to:

Show answer & explanation

Correct answer: D - Install a second rod at least 6 feet from the first; no test of the pair is required

Question 10

A detached workshop is supplied by a four-wire feeder and has a local grounding electrode system. A clamp meter shows normal load current on the feeder equipment grounding conductor and bonded metal water piping. Inspection finds the feeder neutral bar bonded to the panel enclosure. To remove the objectionable current without defeating required grounding, the electrician should:

Show answer & explanation

Correct answer: A - Isolate the neutral bar; retain the feeder EGC and all required equipment, piping, and electrode bonding

The rest of the OK-ELEC blueprint

The OK-ELEC exam also covers these domains. Drill them in the full free practice test:

That's 10 of 1,030

The full bank has 1,020 more OK-ELEC questions with explanations.

Continue in the free practice test →

View plans